05sportsman
Registered
- Messages
- 48
- Reaction score
- 0
- # of dives
I had a question by PM the other day as to weather or not a sticker would replace the VE stamp at hydro and this is to answer that, but I thought it would be beneficial for all to be able to read this.
Per CFR 49 2010:
§ 180.213 Requalification markings
(a) General. Each cylinder requalified in accordance with this subpart with acceptable results must be marked as specified in this section. Required specification markings may not be altered or removed.
(b) Placement of markings. Each cylinder must be plainly and permanently marked on the metal of the cylinder as permitted by the applicable specification. Unless authorized by the cylinder specification, marking on the cylinder sidewall is prohibited.
(1) Requalification and required specification markings must be legible so as to be readily visible at all times. Illegible specification markings may be remarked on the cylinder as provided by the original specification. Requalification markings may be placed on any portion of the upper end of the cylinder excluding the sidewall, as provided in this section.
(c) Requalification marking method. The depth of requalification markings may not be greater than specified in the applicable specification. The markings must be made by stamping, engraving, scribing or other method that produces a legible, durable mark.
(d) Requalification markings. Each cylinder that has successfully passed requalification must be marked with the RIN set in a square pattern, between the month and year of the requalification date. The first character of the RIN must appear in the upper left corner of the square pattern; the second in the upper right; the third in the lower right, and the fourth in the lower left. Example: A cylinder requalified in September 1998, and approved by a person who has been issued RIN A123, would be marked plainly and permanently into the metal of the cylinder in accordance with location requirements of the cylinder specification or on a metal plate permanently secured to the cylinder in accordance with paragraph (b) of this section. An example of the markings prescribed in this paragraph (d) is as follows:
Where:
9 is the month of requalification,
A123 is the RIN,
98 is the year of requalification, and
X represents the symbols described in paragraphs (f)(2) through (f)(7) of this section.
(e) Size of markings. The size of the markings must be at least 6.35 mm (1/4 in.) high, except RIN characters must be at least 3.18 mm (1/8 in.) high.
(f) Marking illustrations. Examples of required requalification markings for DOT specification and special permit cylinders are illustrated as follows:
(3) For designation of special filling limits up to 10% in excess of the marked service pressure for cylinders conforming to §173.302a(b) of this subchapter, the marking is as illustrated in paragraph (d) of this section, except that the X is replaced with a plus sign +.
(9) For designation of the eddy current examination combined with the visual inspection, the marking is as illustrated in the paragraph (d) of this section, except the "X" is replaced with the letters "VE".
If anyone has any other questions let me know, I will try to keep up with this thread. Thanks
Per CFR 49 2010:
§ 180.213 Requalification markings
(a) General. Each cylinder requalified in accordance with this subpart with acceptable results must be marked as specified in this section. Required specification markings may not be altered or removed.
(b) Placement of markings. Each cylinder must be plainly and permanently marked on the metal of the cylinder as permitted by the applicable specification. Unless authorized by the cylinder specification, marking on the cylinder sidewall is prohibited.
(1) Requalification and required specification markings must be legible so as to be readily visible at all times. Illegible specification markings may be remarked on the cylinder as provided by the original specification. Requalification markings may be placed on any portion of the upper end of the cylinder excluding the sidewall, as provided in this section.
(c) Requalification marking method. The depth of requalification markings may not be greater than specified in the applicable specification. The markings must be made by stamping, engraving, scribing or other method that produces a legible, durable mark.
(d) Requalification markings. Each cylinder that has successfully passed requalification must be marked with the RIN set in a square pattern, between the month and year of the requalification date. The first character of the RIN must appear in the upper left corner of the square pattern; the second in the upper right; the third in the lower right, and the fourth in the lower left. Example: A cylinder requalified in September 1998, and approved by a person who has been issued RIN A123, would be marked plainly and permanently into the metal of the cylinder in accordance with location requirements of the cylinder specification or on a metal plate permanently secured to the cylinder in accordance with paragraph (b) of this section. An example of the markings prescribed in this paragraph (d) is as follows:
Where:
9 is the month of requalification,
A123 is the RIN,
98 is the year of requalification, and
X represents the symbols described in paragraphs (f)(2) through (f)(7) of this section.
(e) Size of markings. The size of the markings must be at least 6.35 mm (1/4 in.) high, except RIN characters must be at least 3.18 mm (1/8 in.) high.
(f) Marking illustrations. Examples of required requalification markings for DOT specification and special permit cylinders are illustrated as follows:
(3) For designation of special filling limits up to 10% in excess of the marked service pressure for cylinders conforming to §173.302a(b) of this subchapter, the marking is as illustrated in paragraph (d) of this section, except that the X is replaced with a plus sign +.
(9) For designation of the eddy current examination combined with the visual inspection, the marking is as illustrated in the paragraph (d) of this section, except the "X" is replaced with the letters "VE".
If anyone has any other questions let me know, I will try to keep up with this thread. Thanks