Vets going through a "Renourishment Project"

Please register or login

Welcome to ScubaBoard, the world's largest scuba diving community. Registration is not required to read the forums, but we encourage you to join. Joining has its benefits and enables you to participate in the discussions.

Benefits of registering include

  • Ability to post and comment on topics and discussions.
  • A Free photo gallery to share your dive photos with the world.
  • You can make this box go away

Joining is quick and easy. Log in or Register now!

undrwater

Contributor
Messages
7,620
Reaction score
7,528
Location
Cerritos, CA
# of dives
200 - 499
http://www.mercurynews.com/californ...-rey-dredging-project-replenish-redondo-beach

The project - which will last about 40 days - calls first for depositing roughly 85,000 cubic yards of marina sediment into water depths of 30-50 feet near the Topaz Street jetty.
...
The focus then will shift to a section of narrowed beach between the Topaz jetty and Ruby Street, he said. There, about 75,000 cubic yards of sediment will be pumped onto the sand from a barge anchored 1,000 feet off the coastline.
...
Bulldozers will spread the sand across the beach, and workers will shift the pipe opening periodically to ensure the material is evenly distributed.

Apparently this was done before in 2000. Anyone have recollections about this, and how it impacted conditions? Also, since they call it "nourishment", can we eat it? :rofl3:
 
A bright red tug was pulling the loaded barge towards Topaz jetty this morning at 10 AM.